Ocean Heights 1, Dubai Marina - Project Updates

May 28, 2009

50th floor core work in progress

May 28, 2009
57th floor form work in progress

May 18, 2009
55th floor structural work in progress

May 11, 2009
52nd floor slab work in progress

April 28, 2009
3 chillers weighing more than 16 tonnes each have been installed on the basement floor. 4, 000 fire alarm points will be installed. In addition more than 50, 000 meters of piping for hot and cold water will be used in the building together with 23, 000 meters of drainage pipes

February 17, 2009
Glass work in progress

December 21, 2008
32nd floor structural work in progress

July 10, 2008
The tower will feature 9 units of Signature Series Apartments from the 67th to the 75th floor & Duplex Apartments from the 76th to the 81st floor

July 10, 2008
10 floors have been completed

March 04, 2008
The tower is 310 meters tall

February 11, 2008
Basement level currently under construction

June 29, 2007
The main contractor is expected to be awarded by July 2007

May 16, 2007
The penthouse consists of home entertainment, in a 5-star with a large screened television, generous speakers, surround sound system and a study room

March 28, 2007
Piling work in progress

February 26, 2007
The main contractor has not been awarded

February 24, 2007

November 08, 2006
Piling work is expected to be completed in January 2007

November 08, 2006
The main construction contract is expected to be awarded in December 2006

September 13, 2006
The main contractor has not been awarded as yet

March 13, 2006
The 2nd piling stage is expected to commence within 2 weeks

February 09, 2006
Foundation work in progress

February 09, 2006
Building Permit No. 133040-1-4

December 17, 2005
Tenders for the main construction package will be invited after the piling work has been completed, which is expected in the early 2006

July 10, 2005
The detailed design of the project is currently in progress

(Source: Miscellaneous Data)